Moving SMART™ Boards
This page provides process instructions for moving existing SMARTâ„¢ Boards (board, speakers, projector, and all accessories) to another location. This process can also be used to simply reinstall or uninstall SMART equipment as well.
Moving a SMART Board will typically involve both CBE Facilities and Environmental Services (FES) and our current Audio Visual Vendor (Sharps AV). FES may be required to perform any structural, electrical, or data installation and the vendor will be involved in the testing, removal, and installation of the product being relocated.
To start the process, follow the steps below.
To start the process please compose an email to the CBE Helpdesk at helpdesk@cbe.ab.ca or Click Here to begin a new email message.
This email should include your key contact information including your name, school, principal name, and the total number or rooms / products you require. Also please complete the remaining steps below.
hide step 1
CBE SMART Move Form
Click Here to download the CBE SMART Form. Please download and complete the following form.
Notes about the form:
- If possible, please make sure as much visible wall space is in the image.
- Show electrical and data outlets
- Vendor costs can be found in Step 3 - Prepare S18
- Include serial numbers if available
- Include room numbers, description, locations, or any additional information
- Submit form with email to the Helpdesk
hide step 2
When filling out the S18, please seperate FES and Vendor Costs. Click Here to see an example of a S18.
FES Costs
- FES will charge $200 to complete an onsite quote for any structural, electrical or data requirements. This is for both the existing and new locations of the product.
- This quote will include any cleanup (patch / paint / filling) once the product is removed.
- Include this $200 charge on the S18.
- This charge is not per room (one charge if moving more than one)
- If the move request is cancelled or any stop in the process is made, after the onsite quote is completed, the $200 charge would still be processed.
- For clarification or other FES related questions, please call Dale Burton at 403-214-1158
Click Here to learn more about FES Costs
Vendor Costs
- To uninstall / reinstall (move) - $1,150
- To reinstall only - $970
- To uninstall SMART Board and Projector - $790
- To uninstall SMART Board only - $610
- The prices above include a $250 charge to complete onsite testing and recommendation.
- You do not have to include this on the S18, however if the move request is cancelled or any stop in the process is made, after the onsite testing and recommendation is completed, the $250 charge would still be processed.
hide step 3
Once your email to the CBE Helpdesk includes the images, contact information, descriptions etc. you can the send it. Once it received at the Helpdesk, a CBE HEAT ticket will be created. This information will then be sent to CBE Facilities and to our current vendor.
Both the vendor and FES will then schedule a time with the key contact to visit the school and complete two quotes. Once the quotes are completed, you will either approve, decline, or change them. If you approve the quotes, you will sign them and send them back to FES, Vendor, and the Helpdesk.
The Helpdesk will update the CBE HEAT Ticket with the two quotes and notification to schedule and complete the move will occur next. Both the vendor and FES will coordinate with the key contact a time that the work can be completed.
hide step 4
Once the quotes are approved and processed, any structural work has been completed, and the product move has occurred, the vendor will 'sign-off' on the relocate by sending a Quality Control document back to the CBE Helpdesk. This will then be sent to the key contact listed in step 1.
It is important to note that once the vendor has signed off on the installation, there is a 90 day "bumper to bumper" warranty on the installation. If any product requires service please contact the CBE helpdesk so they can schedule a service call. Once the 90 day warranty is complete, service calls to the school will include additional service charges.
hide step 5